Natural England – update on European licences delays : 16/2/15

We thought an update of statistics on our previous article might be of assistance.

Natural England are still unfortunately experiencing delays in reviewing European Protected Species Licence applications.  It looks like the situation with bats has slightly worsened, although the issues with great crested newts now appear to have improved.  They are training more staff, but our forecast is for no improvement in the immediate to near future.

Bat Update (as of 16th February 2015)

  • 355 ‘New’ Applications outstanding [ Up from 279 on 22 December ]
  • “New application processing time: Average delay of 18 days (48 days versus 30 working day decision deadline) [ Increase from 17 days on 22 December ]

Great Crested Newt Update (as of 16th February 2015)

  • 52 ‘New’ Applications outstanding [ Up from 19 on 22 December ]
  • “New” application processing time: Average delay of 2 days (32 days versus 30 working day decision deadline) [ Down from 7 days on 22 December ]

If you are concerned about gaining a licence, please contact us as soon as possible.